1.Precon Test(Preconditioning Test)
Purpose of Precon Test:To know the workability of Semiconductor devices after soldering.
It simulates delivery from assembly house to customers plant and soldering on PCB.
Defects after Precon Test:Package Crack,Delamination,Electrical Open/Short.
2.Reliability Test
Purpose of Rel. Test:To know the workability of Semiconductor devices after Board Mounting in Real Situations which can be induced by actual users.
Procedure of Reliability Test:
1)T/C Test(Temperature Cycling Test)
Purpose of T/C:To know the durability of Semiconductor package resisting expansion and shrinkage by high and low temperature.
Test Conditions:Temp:+150/-65deg.C;Time:15min/zone;Read-out Point:1000 cycle ;Measurement ; Open/Short Test .
Failures after T/C Test :Open due to Bond Lift or Ball Neck Broken by the chip surface Delamination ,Short due to Cracked Die.
Open Failure after T/C Test:Die Top Delamination & Ball Neck Broken .
2)T/S Test(Thermal Shock Test)
Test Conditions :Temp:+150/-65℃;Time : 15 min/ zone;Read-out Point : 1000 cycle;Measurement;Open/Short Test.
3)HTST(High Temperature Storage Test)
Purpose of HTST:To know the durability of Semiconductor package when exposed under the high temperature for long time.
Test Conditions:Temp:150℃;Read-out Point:1000HRS;Measurement;Open/Short Test.
4)T&H Test(Temperature & Humidity Test)
Purpose of T&H Test:To know the durability of Semiconductor PKG under the high temp and humidity condition .
Test Conditions:Temp:85℃; Humidity:85%;Read-out Point:1000HRS;Measurement;Open/Short Test.
5)PCT(Pressure Cooker Test)
Purpose of PCT:To know the existence of gap between EMC & L/F .
Test Conditions:Temp:121℃;Humidity:100%;Pressure:2ATM;Read-out Point : 168HRS;Measurement;Open/Short Test.
6)HAST(Highly Accelerated Stress Test)
Purpose of HAST:To know the existence of gap between EMC & Substrate.
Test Conditions:Temp:130℃;Humidity:100%,Pressure:33.3Psi;Read-out Point : 96HRS;Measurement;Open/Short Test.